Important Dates
 |  |  | | Dates | Item | Description | | August 29 - October 27, 2011 | Simulation |
During simulation, system users such as traders, back-office staff, in-house developers as
well as data vendors and ISVs can take advantage of simulating existing and new features
provided with the new software release. The simulation calendar provides complete
information about simulation.
| | October 28, 2011 | Distribution of production kit & not |
Distribution of the information/software upgrade necessary to participate in production.
| | November 5, 2011 | Connection test | Testing of connectivity to ensure operational readiness by launch. | | November 7, 2011 | Production start |
Please note that the introduction of specific components of the new release may happen
later than the regular production launch date. The exact dates are published in separate
circulars with sufficient lead times.
|

|  |